The "Project Particulars" section of the Project Dashboard contains all the information to do with the project, as defined in Reg.6 of the Construction (Design and Management) Regulations 2015.

You can edit these details at any time, but try to get them as complete as possible early on so that new participants in the project can see the up-to-date details when they join. 

This information includes:

The address of the construction site or a precise description of its location.

The name of the local authority where the construction site is located.

A brief description of the project type and the construction work that it entails.

The time allocated for the construction work by the client under regulation 4(1)

The start date planned for the construction phase.

The planned duration of the construction phase.

The estimated maximum number of people at work on the construction site.

The planned number of contractors on the construction site.

The Budget for the project.

Current and Previous use of the Site.

Details of any existing Structures.

Specific Toggles which allow you to "auto eliminate" sections of the HARI based on elements that do or don't exist on site.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article